Carnarvon Project with Rig AD-1 near Phi Chit ( Thailand )
Preparations for mobilizing AD-1 from Mae Sot ( Thailand ) to a location near Phi Chit ( Thailand ) are underway.
Carnarvon Petroleum ( Thailand ) Ltd. has contracted AD-1 to drill two wells in Block L20/50 with potentially one contingency well to follow.
First well CVN - 5 commenced on 31st January 2011 and successfully completed on 19th February 2011. Nowadays, going to next well CVN - 3 and commencing from 27th February 2011 and successfully completed on 20th March 2011. The rig is currently stacked on the CVN - 3 well site, location in Thailand.